During the construction process, if there is a design adjustment that changes one of the following contents, the investor must request the adjustment of the construction permit. LSX Lawfirm will give you an article about: “Cases where investors have to adjust construction permits in Vietnam”, as follows:

Law on construction 2014

Circular No. 15/2016/TT-BXD

Cases where investors have to adjust construction permits in Vietnam

Firstly, change the architectural form of the work’s exterior; for works in urban areas in areas with requirements on architectural management.

Secondly, change one of the factors of location, construction area; scale, height, number of floors of the work and other factors affecting the main load-bearing structure.

Thirdly, when adjusting the design inside the building, it changes the use function; affecting the safety; fire and explosion prevention and fighting, and environmental protection.

Dossier of application for modification of a construction permit in Vietnam

Dossier of application for modification of a construction permit includes:

Firstly, for the project about Cases where investors have to adjust construction permits in Vietnam

  • An application form for adjustment of construction permit, made according to the form in Appendix 2 of Circular 15/2016/TT-BXD.
  • The original of the issued construction permit.
  • A copy or file containing the original copy of the design drawing of the ground, elevation, sectional section, and work item for adjustment at the scale of 1/50 – 1/200.
  • A copy or file containing a photocopy of the original document approving the design adjustment of the competent person as prescribed, enclosed with the declaration of capacity conditions of the designing organization or individual; in case the design is not appraisal by a specialized construction agency or a report on design appraisal results. Adjusted by a specialized construction agency in accordance with the law on construction.

Secondly, for individual houses about Cases where investors have to adjust construction permits in Vietnam

  • An application form for adjustment of construction permit, made according to the form in Appendix 2 of Circular 15/2016/TT-BXD.
  • The original of the issued construction permit.
  • A copy or file containing a copy of the original design drawing of the ground; elevation; sectional section, and work item proposed for adjustment in scale 1/50 – 1/200. In case of request to be appraised by a specialized construction agency, the report on design appraisal results must be submitted.

Some notes on adjusting construction permits in Vietnam

  • Firstly, in case the construction design of the work has been appraised by a specialized construction agency; the design drawings as prescribed above are copies or the file containing the snapshots of the construction design drawings already approved construction agency specialized in appraisal.
  • Secondly, contents of the revised construction permit are recorded directly in the issued construction permit or recorded in a separate appendix and are an integral part of the issued construction permit.

Along with clarifying “What is construction planning in Vietnam?”, we would like to send you information about types of construction planning according to current laws such as: Bases for formulating construction planning, you can also refer to the article: Responsibility to collect comments on construction planning in Vietnam. You can also refer to these article about review of construction planning.

Related questions about Cases where investors have to adjust construction permits in Vietnam

What means of construction permit?

Construction permit means a legal document granted by a competent state agency to a project owner for construction, repair, renovation or relocation of a work.

Construction permit with a definite period means?

It means a construction permit granted for construction of a work or separate house within a given duration under the plan for implementation of the construction master plan.

Phased construction permit means?

Phased construction permit means a construction permit granted for every part of a work or every work of a project when the construction design of the work or project is not yet completely implemented.

Contact LSX Lawfirm

Finally, hope this article is useful for you to answer the question about: “Cases where investors have to adjust construction permits in Vietnam”. If you need any further information, please contact  LSX Law firm : +84846175333 or Email: [email protected]